Problem

2013 AIME II Problem 7

A group of clerks is assigned the task of sorting 1775 files. Each clerk sorts at a constant rate of 30 files per hour. At the end of the first hour, some of the clerks are reassigned to another task; at the end of the second hour, the same number of the remaining clerks are also reassigned to another task, and a similar assignment occurs at the end of the third hour. The group finishes the sorting in 3 hours and 10 minutes. Find the number of files sorted during the first one and a half hours of sorting.

Leading zeroes must be inputted, so if your answer is 34, then input 034